How to open a restaurant in Dubai: eleven steps, the authority for each and how long it takes

The eleven steps to open a restaurant in Dubai in 2026: trade licence, Ejari, kitchen layout approval, Civil Defence, food permit, staff and timeline.

Opening a restaurant in Dubai is a chain of approvals from four authorities, and the order matters more than the fees. The Department of Economy and Tourism (DET) licenses the company. Dubai Land Department registers the lease. Dubai Municipality approves the kitchen before it is built and inspects it afterwards. Dubai Civil Defence signs off the fire systems. Get the order wrong and you pay rent on a unit you cannot open.

This guide sets out the steps in sequence for restaurants in general: full-service and casual dining, quick service and, briefly, delivery-only kitchens. Each step names the authority, the time it usually takes and where the figure comes from. We checked the government service pages in November 2026 and say where a number is official. Where it comes from a consultancy, we call it an industry estimate and give the month.

We opened seven cafés in Dubai and Sharjah, and five are trading today. If your plan is a café, our guide on how to open a café in Dubai is the closer fit. For the fees line by line, see what a restaurant licence costs in Dubai. Nothing here is legal, tax or financial advice.

Key takeaways

  1. A restaurant in Dubai needs approvals from four authorities in a fixed order: DET for the licence, Dubai Land Department for Ejari, Dubai Municipality for the kitchen and Dubai Civil Defence for fire safety.
  2. Dubai Municipality must approve the kitchen layout before construction starts, the service is free and the municipality aims to respond within three working days.
  3. The trade name costs AED 620 on the Invest in Dubai portal, and DET's set-up tool estimates three working days for a mainland restaurant licence.
  4. Licensing paperwork takes three to six weeks on a clean file on June 2026 industry estimates, but fit-out and Civil Defence stretch a full opening to four to six months.
  5. A franchise keeps every government step and adds a franchise agreement, a ready kitchen design and training before opening.

Decide the format before the paperwork

Page 3

The format decides the licence activity, the size of the kitchen and the fit-out bill. DET's activity list on the Invest in Dubai portal has separate entries for Restaurant (code 5610001) and Cafeteria (5610003), along with Floating Restaurant and Multi Restaurants Center. A full-service or casual dining room with a cooking line belongs under the restaurant activity. Dubai Municipality checks the kitchen against the activity on the licence, and a mismatch stalls the file.

DET's set-up tool attaches three conditions to the restaurant activity. Decoration works must go to a contractor accredited by Dubai Municipality. The food preparation area must fit the processes on the menu, and the tool gives an average of 400 sq ft for a restaurant. The food area layout goes to the municipality for approval when the licence is issued.

Then choose the jurisdiction. A mainland licence from DET lets you trade with the public anywhere in Dubai. A free zone licence confines the business to that zone. Since 1 June 2021, new mainland licences in most activities can be 100% foreign-owned under Federal Decree-Law No. 26 of 2020, so a dine-in restaurant no longer needs a local majority partner.

Size follows format. Contractor rates published in July 2026 put quick-service fit-out at AED 550 to 900 per sq ft and casual dining at AED 700 to 1,200. The budget for each format is in our guide to the cost to open a restaurant in Dubai.

The eleven steps and the authority for each

Page 4

The approvals run in sequence. Each one is a condition for the next.

  1. Concept and format. You decide the menu, the service style and the licence activity. No authority is involved yet, but every later approval tests this choice.
  2. Company and trade name. DET, through the Invest in Dubai portal. The trade name costs AED 620 and the portal completes the request within 10 minutes.
  3. Initial approval and trade licence. DET. Initial approval comes before the lease. DET's set-up tool estimates three working days for a mainland licence.
  4. Site, lease and Ejari. The landlord, then Dubai Land Department. Ejari registration costs AED 177.75 online or AED 220 at a trustee centre on the department's fee list.
  5. Kitchen layout approval. Dubai Municipality's Food Safety Department, before any construction. The service is free and the municipality aims to respond within three working days.
  6. Fit-out and Civil Defence. Dubai Civil Defence approves the fire safety design and inspects the finished systems.
  7. Person in Charge. A manager certified in food safety by a training centre that Dubai Municipality has approved.
  8. Staff visas and health cards. The company needs establishment cards from the residency authority and the labour ministry before it can sponsor staff. Every food handler needs an occupational health card.
  9. Inspection and food permit. Dubai Municipality inspects the finished kitchen.
  10. FoodWatch. The municipality's digital food safety platform, where the business registers its primary Person in Charge.
  11. Opening. The licence, the permit and the sign are in place, and the first service can run.

Invest in Dubai lists twelve screens for the company part alone, from selecting activities to additional approvals. The table below gives the typical time for each step and the source.

Steps to open a mainland restaurant in Dubai, with the authority, typical time and source for each (official figures checked November 2026; consultancy figures are dated industry estimates)
StepAuthorityTypical timeSource
1. Concept, format and licence activityOperator, using DET's activity listYour own planning timeInvest in Dubai activity search
2. Company and trade nameDepartment of Economy and Tourism (DET)Within 10 minutes onlineInvest in Dubai service page
3. Initial approval and trade licenceDETInitial approval three to five working days; licence about three working daysDIAC, August 2026; Invest in Dubai set-up tool
4. Site, lease and EjariLandlord; Dubai Land DepartmentSet by the lease negotiation; no official time publishedDubai Land Department service page
5. Kitchen layout approvalDubai Municipality Food Safety DepartmentResponse within three working days; one to two weeks with revisionsDubai Municipality service page; DIAC, August 2026
6. Fit-out and Civil DefenceDubai Civil Defence8 to 16 weeks from design submission to final certificateNoble Core Ventures, July 2026 (industry estimate)
7. Person in Charge trainingTraining centres approved by Dubai MunicipalityCompleted before inspectionDubai Municipality Food Code and service page
8. Staff visas and health cardsResidency and labour authorities; approved medical centresRuns alongside fit-outInvest in Dubai; Dubai Business Services, June 2026
9. Inspection and food permitDubai MunicipalityOne to two weeksDIAC, August 2026 (industry estimate)
10. FoodWatch registrationDubai MunicipalityBefore opening; freeDubai Municipality Food Code; DIAC, August 2026
11. OpeningOperatorFour to six months from first call to opening for our franchised cafésThe Bhukkad Café, management estimate

Site, lease and Ejari

Page 5

The lease starts the clock. From the day it is signed, rent runs whether or not the kitchen is approved.

Check three things before signing. First, that the unit can take the kitchen: an extraction route, grease management, enough power or gas, and floor space for the food area the activity needs. Second, the rent against published benchmarks. Broker figures from March 2025 put prime malls at AED 700 to 900 per sq ft a year, community malls and high streets at AED 250 to 400 and emerging areas at AED 150 to 250. Third, the date rent starts, which in a mall lease can fall before the fit-out is finished.

Ejari is the registration of the tenancy contract with Dubai Land Department. The department lists the documents as the unified tenancy contract and the applicant's Emirates ID, with a power of attorney if a representative applies. A mainland restaurant licence is tied to a physical location, so the registered lease has to exist before the licence can be completed.

Kitchen layout, fit-out and Civil Defence

Page 6

Dubai Municipality's service page is plain about the order. Approval of the design, layout, equipment and process flow is required before construction of a food establishment starts, or before a major renovation of a commercial kitchen. The application needs a scaled layout that shows the receiving, processing, storage and utility areas, with equipment specifications. Approval removes the Food Safety Department's remark from the trade licence.

The same page says no alteration, addition or deletion can be made to an approved layout without the municipality's authorisation. A change to the space, the preparation areas, the equipment positions or the process flow needs a new approval. Design the kitchen for the menu you will cook, get it approved and build exactly that.

Civil Defence runs alongside. A July 2026 industry guide from Noble Core Ventures puts the cycle from design submission to final certificate at 8 to 16 weeks for a food and beverage fit-out. It names fire alarm, sprinkler changes and kitchen hood suppression as the main works. Those durations are estimates, and they are usually the longest single item in an opening. Appoint the fire consultant with the fit-out contractor, not after.

People, the Person in Charge and inspection

Page 7

The Dubai Municipality Food Code has required a certified Person in Charge in every food establishment since 2010. High-risk operations need one on every shift, and each business registers a primary Person in Charge on FoodWatch. The municipality approves the trainers and training centres that deliver the course. An August 2026 estimate from Dubai International Advisory Consultants puts the certificate at AED 300 to 500 per person.

Every food handler needs an occupational health card, quoted at AED 300 to 600 per person per year by Dubai Business Services in June 2026. Staff also need employment visas, medical tests and Emirates IDs. Start these as soon as the licence is issued. A full-service restaurant has more people to process than a café, and the cards should be in hand before inspection.

The municipality then inspects the finished kitchen. Dubai International Advisory Consultants allows one to two weeks for the inspection and the review of the food safety documents. It adds that a kitchen which fails its first inspection can push the licensing chain past eight weeks. FoodWatch registration is free.

A week-by-week timeline

Page 8

No authority publishes a single timeline, so this one is built from the durations above. Treat it as a planning sketch for a mainland restaurant in a unit that needs a full fit-out.

  • Weeks 1 to 2. Trade name, initial approval and a shortlist of sites. Initial approval takes three to five working days on the August 2026 estimate.
  • Weeks 2 to 4. Lease signed, Ejari registered, licence issued, kitchen drawings prepared and submitted. Allow one to two weeks for layout review with revisions.
  • Weeks 4 to 6. Fire safety design submitted to Civil Defence. The contractor starts once the layout is approved.
  • Weeks 6 to 16. Fit-out, extraction, fire systems and equipment. Staff visas, health cards and Person in Charge training run in parallel.
  • Weeks 16 to 18. Civil Defence inspection, municipality inspection, food permit and FoodWatch registration.
  • Weeks 18 to 20. Stock, staff training in the finished kitchen and a soft opening.

The paperwork alone completes in three to six weeks on a clean file, on Dubai Business Services' June 2026 figure. Construction sets the rest. For our own franchised cafés we plan four to six months from first call to opening, and a full-service restaurant with a larger kitchen should not expect less.

Delivery-only kitchens, alcohol, pork and shisha

Page 9

Delivery-only kitchens follow the same chain with a smaller site and no dining room. Dubai Municipality's layout page says each unit in a shared cloud kitchen must be at least 200 sq ft, with storage, food preparation and equipment washing areas shared between the kitchens. Dubai International Advisory Consultants quotes shared kitchen pods at AED 5,000 to 15,000 a month and two to four weeks to license, as of August 2026.

Alcohol is a separate regime. A March 2017 Q&A by the law firm Al Tamimi & Company says liquor licences in Dubai are issued by Dubai Police under the Liquor Control Law of 1972. A Type C licence covers serving liquor within a hotel, club or restaurant, and service to anyone under 21 is prohibited. Dubai Municipality's fee page lists a municipality fee of 7% of total sales for hotel establishments, their restaurants and other venues that serve alcohol. The law firm's note is several years old, so confirm the current process before you sign a lease that depends on it.

Pork is closed to most restaurants. The municipality's permit page limits new non-halal food permits to four-star and five-star hotels, supermarkets of at least 500 sq m and food trading firms with warehouses. Shisha needs a designated smoking area permit from the municipality. The permit is free, takes five working days and needs ventilation drawings.

Mistakes operators commonly make

Page 10

Starting fit-out before the layout is approved. The municipality's rule is approval before construction, and anything built differently needs a new approval.

Choosing the licence activity by price. The kitchen is checked against the activity. When we ran DET's calculator in November 2026, the restaurant and cafeteria activities returned the same fee estimate at the same rent, so the cheaper-code idea saved nothing.

Signing for a unit that cannot take the kitchen. Extraction and floor area are fixed by the building. The licence cannot fix them later.

Leaving Civil Defence to the end. On the industry estimates above it is the longest approval, and rent is running throughout.

Ordering the sign before reading the rules. The Dubai Media Office restated them in May 2026. DET issues the permit for trade-name signage, each shopfront shows one trade name, the sign runs horizontally and Arabic sits above English.

Treating a consultancy quote as the official fee. The municipality's layout approval is free, yet one April 2026 consultancy guide lists AED 500 to 1,000 for it. Check each line against the government page before you pay.

Where a franchise changes the steps

Page 11

A franchise removes none of the government steps. The franchisee's company still holds the licence, signs the lease and passes the inspections. The difference is in what you bring to each one.

Step one arrives finished. The menu, the format and the kitchen design come from the franchisor, and a layout that has been approved before is less likely to come back with comments. One step is added before the lease: the franchise agreement. The UAE has no standalone franchise law. Pinsent Masons' October 2025 guide places franchising under the Commercial Agencies Law of 2022 and general contract law. Outside a few regulated industries, registering the agreement with the Ministry of Economy is optional. A registered agreement generally needs a franchisee that is a UAE national or a company at least 51% UAE-owned, so ask the franchisor which route it expects. Check too that the brand's trade mark is registered in the UAE.

Training moves ahead of opening. In our own system the owner and manager train for 14 to 21 days, our trainers are on site for 10 to 15 days around opening, and stock and packaging come through approved suppliers. The franchise fee is AED 110,000 per outlet, with a royalty of 7% of gross sales, at least 2% spent on local marketing and up to 1% paid into a brand fund. Our formats run from Express units of up to 500 sq ft at AED 600,000 to 630,000 all-in, through cafés of 500 to 1,000 sq ft at about AED 1.05 million, to Flagship sites of 1,000 to 3,000 sq ft at about AED 1.7 million. These are management estimates for the UAE as at October 2026 and vary by site. Outcomes vary and nothing is guaranteed. The terms are on our franchise page, and the process is in our guide on how to open a franchise in Dubai.

Frequently asked questions

Page 12

How long does it take to open a restaurant in Dubai?

Plan for four to six months from the first application to opening day. The licensing paperwork takes three to six weeks on a clean file, on Dubai Business Services' June 2026 estimate. Fit-out and Dubai Civil Defence approval take longer: a July 2026 industry guide puts the fire approval cycle at 8 to 16 weeks for a food and beverage fit-out. A unit with a compliant kitchen already in place can be quicker.

Which licence do I need to open a restaurant in Dubai?

Two approvals. The Department of Economy and Tourism issues the trade licence with a restaurant activity, listed as code 5610001 on the Invest in Dubai portal. Dubai Municipality's Food Safety Department approves the kitchen layout before construction and inspects the finished premises. Dubai Civil Defence must also approve the fire systems, and the lease must be registered through Ejari.

Can a foreigner own 100% of a restaurant in Dubai?

Yes, on the mainland. Federal Decree-Law No. 26 of 2020 has applied to new mainland licences since 1 June 2021 and allows full foreign ownership in most activities, restaurants included. One exception concerns franchises: an agreement registered with the Ministry of Economy generally needs a franchisee that is a UAE national or a company at least 51% UAE-owned. Registration is optional for restaurants.

Do I need Dubai Municipality approval before fit-out?

Yes. Dubai Municipality's service page says approval of the design, layout, equipment and process flow is required before construction of a food establishment or a major kitchen renovation. The service is free, and the municipality aims to respond within three working days. Changes to an approved layout need a new approval, so build what was approved.

Can a restaurant in Dubai serve alcohol?

Only with a separate liquor licence. A 2017 Q&A by the law firm Al Tamimi & Company says Dubai Police issue the licences under the Liquor Control Law of 1972, and that a Type C licence covers service within a hotel, club or restaurant. Dubai Municipality also lists a fee of 7% of total sales for venues that serve alcohol. Confirm the current rules before committing to a site.

What is a Person in Charge, and does every restaurant need one?

Yes, every restaurant needs one. The Dubai Municipality Food Code has required each food establishment to have a certified Person in Charge since 2010. High-risk operations need one on every shift, and each business registers a primary Person in Charge on the FoodWatch platform. Training centres approved by the municipality deliver the course, at AED 300 to 500 per person on an August 2026 industry estimate.

Is a delivery-only kitchen easier to open than a restaurant?

It follows the same licence chain with a smaller site and no dining room. Dubai Municipality says each unit in a shared cloud kitchen must be at least 200 sq ft, with storage, preparation and washing areas shared between kitchens. An August 2026 industry estimate puts a shared kitchen pod at AED 5,000 to 15,000 a month and two to four weeks to license.

Does a franchise restaurant need the same permits?

Yes. The franchisee's company holds the trade licence, registers the lease and passes the Dubai Municipality and Civil Defence inspections like any other operator. The franchise adds a franchise agreement before the lease, a kitchen design that has been approved before and training before opening. At The Bhukkad Café we plan four to six months from first call to opening.

Sources

  1. Invest in Dubai (Dubai Department of Economy and Tourism), business set-up steps
  2. Invest in Dubai, request to book a trade name (fee AED 620)
  3. Invest in Dubai, business set-up recommendation and cost calculator, Restaurant activity 5610001 (run in November 2026)
  4. Dubai Municipality, Approval of the Design Layout for Food Establishments (service page, last modified 20 March 2025)
  5. Dubai Municipality, Permit for Food Related Activities (fees and eligibility)
  6. Dubai Municipality, Permit for Designated Smoking Area or Selling Tobacco and Related Products
  7. Dubai Municipality, fees on hotel and entertainment establishments sales
  8. Dubai Municipality, Approval for Food-Related Establishments (food safety trainers and training centres)
  9. Dubai Municipality Food Code and FoodWatch platform (Person in Charge requirements)
  10. Dubai Land Department, register or renew a tenancy contract (Ejari fees and documents)
  11. UAE Ministry of Economy, 100% foreign ownership under Federal Decree-Law No. 26 of 2020
  12. Government of Dubai Media Office, shopfront trade-name signage rules (12 May 2026)
  13. Al Tamimi & Company, Liquor Licenses in Dubai, Law Update (March 2017)
  14. Pinsent Masons, Franchising in the UAE (16 October 2025)
  15. Dubai Business Services, restaurant licence cost in Dubai 2026 (23 June 2026)
  16. Dubai International Advisory Consultants, food licence in Dubai (updated 12 August 2026)
  17. Dubai International Advisory Consultants, open a restaurant in Dubai (updated 4 April 2026)
  18. Noble Core Ventures, Civil Defence approval in Dubai (27 July 2026)
  19. Red Rock Real Estate, Dubai retail rent benchmarks (March 2025)